How can SAP MDG create a follow-up work item to maintain BOM, PIR, or Production Versions after a material Change Request is activated?

Use a customer-specific follow-up workflow after the material Change Request is activated: create a dialog work item, send it to the MDG Inbox/POWL, and open a customer Web Dynpro app that receives the Change Request ID and Work Item ID so users can maintain BOM, PIR, PV, or similar related objects outside the closed CR.

Use a customer-specific follow-up workflow after the material Change Request is activated: create a dialog work item, send it to the MDG Inbox/POWL, and open a customer Web Dynpro app that receives the Change Request ID and Work Item ID so users can maintain BOM, PIR, PV, or similar related objects outside the closed CR.

Use a customer-specific follow-up workflow after the material Change Request is activated. The guide’s pattern is: activate the main material CR, trigger a background follow-up activity, create a dialog work item, show it in MDG Inbox/POWL, and open a custom Web Dynpro application for BOM, PIR, PV, or other related-object maintenance. The UI should provide Actions, Description, and Links, and it must receive both the Change Request ID and the Work Item ID.

Process flow

  1. Process the material master through the normal SAP MDG Change Request.
  2. Activate the Change Request successfully.
  3. Trigger a customer-specific background follow-up workflow.
  4. Create a dialog work item for the related-object maintenance task.
  5. Assign the task to the responsible user group, role, or department.
  6. Expose the work item in MDG Inbox/POWL.
  7. Open a customer-specific Web Dynpro application from the work item.
  8. Provide links to BOM, PIR, PV, or other related-object maintenance transactions/systems in the UI.
MDGIMG

General Setting > Process Modelling > Change Requests > Configure Properties of Change Request Step

Maintain a reduced UI with links to required transactions/systems while the Change Request is still active.

Structure
MDGIMG
Master Data Governance
Classic Mode in SAP MDG
Central Governance
Process Modeling
Change Requests
Configure Properties of Change Request Step
PFCG

Role maintenance with object-based navigation (OBN)

Allow navigation from the follow-up work item to the customer Web Dynpro application.

Referenced tables

ObjectPurpose
IBO_C_WF_TACSource-supported workflow task customizing reference for the follow-up scenario.
IBO_C_WF_TTACSource-supported task-to-action customizing reference for the follow-up scenario.
USMDCREQUESTPROCESSMust not be maintained for the follow-up task, per the guide.

The remaining configuration, implementation details, and testing guidance continue from this answer more…

Related questions and keywords

Alternative questions

  • How can I maintain BOM after an MDG material Change Request?
  • How do I create a follow-up work item after material activation?
  • How can Purchasing Info Records be maintained as a follow-up activity?

Possible questions

  • What is the recommended MDG pattern for post-activation maintenance of related objects?
  • Which configuration objects are needed for a follow-up workflow after MDG activation?
  • How do I pass Change Request and Work Item IDs to a follow-up Web Dynpro app?
  • How do I add the follow-up task to the MDG Inbox/POWL?
  • How does the solution differ for SAP Business Workplace and NWBC POWL?

Keywords

SAP MDGMaterialfollow-up work itemBOMBill of MaterialPurchasing Info RecordPIRProduction VersionPVChange RequestactivationworkflowWeb Dynpro ABAPPOWLNWBCPFCGOBNBUS2250CALLUICL_USMD_UI_SERVICESCL_USMD_CREQUEST_POWL