SAP MDG · UTILITIES

How do I create a cost center in SAP MDG with requestor entry, workflow approval, and final replication to S/4HANA?

In SAP MDG, the requestor creates a cost center in the Manage Cost center - Governance app, enters the master data and validations, submits the change request, and an approver processes it from email or My Change Requests Monitoring. After approval, the cost center reaches final approval and becomes available in MDG and S/4HANA.

In SAP MDG, the requestor creates a cost center in the Manage Cost center - Governance app, enters the master data and validations, submits the change request, and an approver processes it from email or My Change Requests Monitoring. After approval, the cost center reaches final approval and becomes available in MDG and S/4HANA.

The standard MDG cost center creation flow starts in Manage Cost center - Governance, where the requestor creates a change request, enters the cost center basic data, address, and joint venture-related details, then runs Check and submits the request. An approver then processes the request from the email link or My Change Requests Monitoring and approves it so the cost center becomes available in MDG and S/4HANA.

Process flow

  1. Log on to Fiori Launchpad as the Cost center Requestor.
  2. Open Manage Cost center - Governance.
  3. Create a new change request by selecting New.
  4. Maintain cost center basic details such as Name, Medium text, Cost center category, Department, Company code, Profit center, and Person responsible.
  5. Open Cost center Address and maintain NAME3, Country, and Region as required.
  6. Open Joint Venture Details and maintain Joint Venture, Equity Type, Recovery indicator, and JV object type as required.
  7. If applicable, maintain Name 1 for the Unit Cost Center scenario.
  8. Run Check and resolve any validation errors until the system shows No errors found for the CR data set. Submit the change request. Log on as a cost center approver and open the CR from the email link or from My Change Requests Monitoring. A
Manage Cost center - Governance

Fiori app

Create and maintain the cost center change request

Manage Cost Center Master Data

Fiori app

Verify the approved cost center in master data

My Change Requests Monitoring

Fiori app

Find change requests assigned to the approver

Display Change Requests

Fiori app

Display the submitted change request

Referenced tables

ObjectPurpose
USMD1210Change request notes table referenced in the related ABAP utility example
USMD120CUsed in the related ABAP utility example to derive change request type
USMD1601Used in the related ABAP utility example to derive process information
CVI_VEND_LINKUsed in the related ABAP utility example for partner-to-vendor lookup logic
BUT000Used in the related ABAP utility example for business partner data

The remaining configuration, implementation details, and testing guidance continue from this answer more…

Related questions and keywords

Alternative questions

  • What is the SAP MDG process for cost center creation and approval?
  • How does the cost center creation workflow work in MDG?
  • How do I test cost center creation in SAP MDG?

Possible questions

  • How do I create a cost center in SAP MDG with requestor entry, workflow approval, and final replication to S/4HANA?
  • What is the SAP MDG process for cost center creation and approval?
  • How do I test cost center creation in SAP MDG?
  • How do I validate cost center hierarchy assignment during MDG approval?
  • What checks run before approving a cost center change request?

Keywords

SAP MDGCost CenterManage Cost center - GovernanceManage Cost Center Master DataMy Change Requests MonitoringDisplay Change RequestsChange RequestWorkflow approvalFinal check approvedControlling areaJoint Venture DetailsCost center AddressHierarchy assignmentS/4HANA replication