How does SAP MDG process a supplier address update from an external supplier portal with approver workflow?
A supplier address update submitted from an external supplier portal should create a record in the MDG integration staging table, be picked up by the scheduled background job, generate a Change Request and approval notification, and then be processed in Fiori via My Change Requests - Monitoring until the approver approves it and the status becomes Final check approved.
A supplier address update submitted from an external supplier portal should create a record in the MDG integration staging table, be picked up by the scheduled background job, generate a Change Request and approval notification, and then be processed in Fiori via My Change Requests - Monitoring until the approver approves it and the status becomes Final check approved.
A supplier address update from an external supplier portal is first written to the MDG integration staging table, then processed by a scheduled background job, which creates or updates the related Change Request and sends a notification to the approver. The approver then opens the request in My Change Requests - Monitoring, checks the address data, and approves it so the supplier Business Partner address is updated in MDG.
Process flow
- Submit supplier address update from the external supplier portal
- Verify a staging-table record exists in SE16N
- Process the record through the scheduled background job in SM37
- Confirm the status is updated to Processed and the CR number is written back
- Verify approver notification is triggered
- Open My Change Requests - Monitoring in Fiori
- Filter to To be processed by me
- Open the Change Request and run Check validation if needed before approval
SE16NMDG integration staging table for Address
Verify the inbound portal request created a staging record with Business Partner ID, address data, and timestamps
SM37Scheduled background job for staging-table processing
Monitor or execute the job that processes the inbound staging record and creates the Change Request
Fiori Launchpad app
Review, validate, and approve the Change Request as the BP approver
Fiori Launchpad app
Display the Change Request details for verification
Referenced tables
| Object | Purpose |
|---|---|
USMD1210 | Change Request note table used in the related BP utility method example |
MDG integration staging table for Address | Inbound staging storage for portal-sent address updates; exact table name is implementation-specific and must be checked in the system |
The remaining configuration, implementation details, and testing guidance continue from this answer more…
Related questions and keywords
Alternative questions
- How is an external supplier portal address change turned into an MDG Change Request?
- What happens after a supplier address update is submitted from an external portal in MDG?
- How do I verify the staging table, background job, and approver workflow for a supplier address change in MDG?
Possible questions
- How does SAP MDG process a supplier address update from an external supplier portal with approver workflow?
- How do I verify the staging table and CR approval for supplier address changes in MDG?
- Which apps and transactions are used to monitor and approve an MDG supplier address change?
- What status should the Change Request reach after approval?
- How do I troubleshoot an external portal supplier address request that is not creating a Change Request?